Works on the Lusaka-Ndola dual carriageway project are progressing well.
The works are ongoing at four different sites on the project corridor.
Today focus is on the 45 kilometres Masangano-Fisenge-Luanshya Road. The Concessionaire is currently working on the drainage structures and 50% progress has been attained on the two structures out of three.
Clearing and grubbing has been achieved on the 32 kilometres stretch of the Masangano-Fisenge-Luanshya. Further, roadbed preparation has been undertaken on the 32 kilometres stretch.