RDA to Enforce Quality International Standards on Lusaka–Ndola  Dual Carriageway Project
NEWS16 November 2026

RDA to Enforce Quality International Standards on Lusaka–Ndola Dual Carriageway Project

RDA to Enforce Quality International Standards on Lusaka–Ndola  Dual Carriageway Project

The Minister of Infrastructure and Urban Development, Hon. Eng. Collins Nzovu, has reaffirmed the Road Development Agency’s (RDA) responsibility to ensure that construction works under the Lusaka–Ndola Public–Private Partnership (PPP) Road Project meet international standards.

Speaking during an inspection of the Lusaka–Ndola Dual Carriageway Project today, the Minister said private sector participation did not diminish the need for rigorous quality control and engineering oversight.

“Yes, we have our private partners working on the road, but any construction must conform to Zambian standards,” he said.

The Minister explained that a full-time consultant had been engaged to supervise the works, a role initially undertaken by RDA.

He expressed satisfaction with the quality of construction, noting that the contractor had been required to redo sections that did not meet the prescribed standards.

“Where we saw that the quality of works was not conforming to the accepted standards, we made the contractor redo those works,” he said.

Hon. Eng. Nzovu added that the concessionaire’s long-term responsibility for maintaining and repairing the road provided a further incentive to deliver durable infrastructure.

He assured the public that RDA engineers, including those based in the provinces, would continue monitoring the works to ensure compliance with the required specifications.


The Minister also appealed to pedestrians and other road users to exercise patience as outstanding ancillary works, including the installation of guardrails and other safety features, were completed. He emphasised that these works were essential to protecting all road users.

Meanwhile, MOIC Consortium L-N Limited Assistant to the Project Manager, Kang Xinyue, said construction was progressing despite challenges posed by underground utilities and seasonal rainfall.

She explained that unforeseen underground cables in urban sections had delayed some works, while heavy rainfall during the previous rainy season had resulted in the loss of approximately one month of construction time.


Despite these setbacks, she said the contractor remained focused on achieving the targeted completion period.

The project traverses Lusaka, Central and Copperbelt Provinces. Its scope includes upgrading 327 kilometres of the Lusaka–Ndola Road to a dual carriageway, rehabilitating 45 kilometres of the Masangano–Fisenge–Luanshya Road, and constructing approximately 30 kilometres of bypass roads in Kabwe and Kapiri Mposhi.

Overall physical progress stands at 89.05 per cent. Asphalt surfacing has been completed on 524.94 kilometres out of a planned total of 662.4 kilometres covering both north and south bound lanes.